North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...

La page est créée Jean-Pierre Auger
 
CONTINUER À LIRE
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
North Area Maintenance weeks and AUG tests
Feedback from users & lessons learned

Additional activities for EN-EL contractor
List of activities and follow-up

EN-EL calendar
LS2 planned maneuvers

D. Bozzini on behalf of EN-EL, 13 October 2020
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
North Area Maintenance weeks and AUG tests
Feedback from users & lessons learned
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
Feedback from users & lessons learned

 EN-EL invited to report on North Area maintenance and AUG tests at
  the ENTM planned for Thursday 15 October 2020
 Request made to main users and stakeholders to provide feedback
  on the four following topics

     Affected systems
     Malfunctions (causes, consequences and measures taken)
     Coordination and planning
     Suggestions for improvement
 Valuable feedback received so far from:
   F. Duval (EP)
   J. Devine (EP) draft in approval state
   TI (BE)
 Presentation to EATM after ENTM conclusions and recommendations

                                                                   3
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
Examples of maintenance activities

Maintenance 18 kV Magrini switchgear
– General Services network
     4 switchgear, 35 feeders, dating
      from 70’, includes busbars &
      ground switch-disconnectors
     Last maintenance performed in
      2005, should be done every 10
                                                          Before                 After
      yrs.
     100% completed
     Switchgear dangerous to operate,
      requiring maintenance < 10 yrs.
      “Risque de désaxage des volets
      en ferraille engendrant un court-
      circuit franc pendant les
      manœuvres de consignation”
                                     “Remplacement visserie HS sur connexion
                                     secondaire transformateur de courant (TC)
                                     dans EMD2/A82, risque d’explosion du TC”

                                                                                         4
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
Examples of maintenance activities

Scheduled corrective intervention on a LV switchboard (sub-distribution) following visual
inspection and routine visits performed during machine operation

  “Risque de mauvaise
  connexion dans le temps,
  départ de feu”

                                          Before                           After
Consolidation AUL system in EHN1 following malfunctioning observed by EP in August 2020
      Replacement of one tripping coil
       and three circuit breakers

                                                                                            5
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
Actions initiated and planned to be done during LS2

 Study for replacement of the following UPS systems
   EBS21/BL4
   EBS22/A81
   EBS21/A85
   EHN1
 Replacement of batteries of the following UPS systems (already part of the EN-
  EL program)
   EBS21/A80
   EBS24/A80
   EBS21/A81
   EBS24/A81
   EBS21/A82
   EBS24/A82
   EBS21/B81
 Completion of 48V system in EHN1

                                                                               6
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
Additional activities for EN-EL contractor
List of activities and follow-up
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
List of activities and follow-up

 Goal is to grant a sufficient workload to EN-EL contractor

 Identification of activities that can be done in the coming months,
  according to infrastructure availability and accessibility

 Common EN-EA / EN-EL table for regular update and follow-up at the
  EATM and/or EACM

                                                                    8
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
List of activities and follow-up
                                                                                              Urgent       Still to be In    Under Study                                 Estimation
Priority     Area       Zone                            Description                   New                                                  EN-EL Status      Date                     Budget                          Comments
                                                                                              (2020)      Confirmed Pipeline    (EA)                                       (kCHF)
   0       EHN1      PPE144      nouvelle installation                                                                  x                  in pipeline     mid-Oct.             100    89955     starts mid-October
   0       EHN1      PPEs        Installation CROME (RP)                                                                x                  in pipeline      Nov.                        RP       after PPE144
   0       EHN1      PPEs        campagne de décablage PPE158, 164, 112, 172                                            x                  in pipeline                          15     55455     already discussed (cable cleaning campaign)
   0       NA        907/908     Projet Monitoring Gaz : mécanique et tirage câbles    x                        x             Philippe                                                 95428     1 week of work, 907/908, budget approval pending
           EHN1,
                                                                                                                                                                                                 work already done with J. Devine (for ??? ALL ???
   0       EHN2,     various     EL non-conformities (AUL replacements/repair)         x                                                   on-going
                                                                                                                                                                                                 AULs)?
           ECN3
                                 nouvelle zone de stockage IRRAD (eclairage,
   1       East Area IRRAD                                                             x                      x                                              2021                5     55456     50/50% budget split between EA and DT
                                 puissance)
                                 Réaménagement de la zone :                                                                                               as from mid-
   1       EHN1      H6-H8                                                             x                      x                   x                                             20     89955     required for 2021 operation (MADMAX)
                                 dépose (décablage, e-a-c, boitiers)                                                                                           Nov.
                                                                                                                                                                                               progressive replacement of AULs, requires EP
   1       EHN1      various     AUL->AUG                                              x                      x                   x                          2021                      55455
                                                                                                                                                                                               approval (DSO discussion on-going)
                                                                                                                                                                                               electrical distribution, needs detailed study with all
   1       EHN1      barack gaz dépose + réinstallation?                               x    dismantling                           x                          2021                  89300/55455 service providers -> work needs to be finished prior
                                                                                                                                                                                               2021 operation
                                                                                                                                             pending
   1       EHN1      AWAKE       installation EL nouvelle salle laser                                         x                                                                      AWAKE     ticket issued, pending approbation
                                                                                                                                           approbation
                                                                                                                                                                                               required for 2021 operation, but finalization of
                                 Aménagement pour
   1       EHN2      PPE211                                                            x                                          x                                                   89955    implementation study required before EL work can
                                 NA64mu/Amber-COMPASS/Muon-e
                                                                                                                                                                                               be considered
   1       ECN3      TCC8        ajouter un coffret de prises (tri-16A + 220V-10A)     x                                                                                         2    55455    minor works for a vacuum pump
                                                                                                                                            already in                                         ASAP si feu vert (financier pour ATLAS et
   1       LHC       ZDC         ZDC ATLAS : Cheminement                                                               x      Gianluca                      20/2021             15    ATLAS
                                                                                                                                            discussion                                         organisationnel pour LHC coordination ACE)
                                                                                                                                            already in                                         ASAP si feu vert (financier pour ATLAS et
   1       LHC       ZDC         ZDC ATLAS : tirage de câbles                                                          x      Gianluca                      20/2021             40    ATLAS
                                                                                                                                            discussion                                         organisationnel pour LHC coordination ACE)
                                                                                                                                            already in                                         Procurement des câbles en cours donc sera basculé
   1       LHC       RPD         RPD ATLAS : tirage de câbles                                                          x      Gianluca                       2021               55    ATLAS
                                                                                                                                            discussion                                         en 2021
                                                                                                                                                                                               2 days of work, (F. Duval - NA62),
   1       ECN3      NA62        cable installation                                    x                      x               Philippe                                                NA62
                                                                                                                                                                                               surface/underground
   1       ALICE     UX25        Alice CV, installation de 8 câbles CR4 UX25           x                                      Philippe                                                ALICE
                                                                                                                                            already in
   1       Meyrin    bldg 2004 rewamping installation CV                                                               x      Gianluca                      Feb-21                      CV       février 2021
                                                                                                                                            discussion
   1       LHC       SND                                                               x                                      Philippe                                                SND/EA     see ECR (2020 + 2021)
   1       EHN1      M1          NA-CONS                                                                                    approved                      Jan/Feb-21           135    NA-CONS    required for 2021 operation
                                                                                                                                           refused                                               VSC and NA-CONS (Yacine as contact) -> required
   1       NA        TCC2        vacuum cable installation (one additional)            x                                    Yacine                       20/2021
                                                                                                                                           initially                                             for 2021 operation
                                                                                                                                           initially not
                                                                                                                            not
   2       East Area galleries   dépose cables DC + signaux                            x                      x                            considered 2020/2021                 10     55456     can be started anytime (EPC work already done)
                                                                                                                            concerned
                                                                                                                                           for LS2
   2       East Area galleries   dépose Terminal Boxes                                 x                      x                                           2020/2021              3     55456     minor works
   2       EHN1      PPE124      eclairage additionel                                  x                                                                    a.s.a.p.             2     55442     minor works
                                                                                                                                              pending
   2       EHN1      HNA272      campagne de décablage 272                                                    x                                                                                  ticket created RQF1614906
                                                                                                                                            approbation
                                                                                                                                                         YETS 21/22                              beneficial to advance? -> needs to maintain 2021
   2       EHN1      3.3kV       transformer consolidation                                                                                 approved
                                                                                                                                                         or ? Earlier                            operation availability
                                                                                                                            routing                                                              not beneficial to do in 2021 -> will be done in YETS
   3       EHN1      Morpurgo NA-CONS                                                                                                                     YETS 21/22
                                                                                                                            under study                                                          21/22 -> DC cabling could be possibly anticipated
                                                                                                                            request
   4       LHCb      Velo                                                                                                                                                                        EL involved? -> LHCb didn't keep request
                                                                                                                            dropped

                                                                                                                                                                                                                                              9
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
EN-EL calendar
LS2 planned maneuvers
Presentations given by B. Saint Sulpice at the TIOC on 7th October 2020
Calendar EN-EL of LS2 activities

         07/10/2020   Manoeuvres EN-EL fin 2020 - V3   11
Calendar EN-EL of LS2 activities
                                                  noir : Validé par les
                                                    utilisateurs, les
                                                    Validé
                                                     coordinations
                                                        et EN/EL

          rouge : Non validé.
       En cours de validation par
           les utilisateurs, les
              coordinations
                ou EN/EL

            07/10/2020              Manoeuvres EN-EL fin 2020 - V3        12
EN-EL - Manœuvres en Octobre
                                                                                         réseaux affectés
                                 BE - Tests compensateur BEQ1 (TE-EPC) –             Réseaux machine SPS
                                 Transfert de charges                                Zone Nord

                                 LHC2 - Tests compensateur (TE-EPC)                  Réseaux machine LHC2

                                 BE - Tests compensateur BEQ2 (TE-EPC) –             Réseaux machine SPS
                                 Transfert de charges                                Zone Nord

                                                                                     Réseaux SG et machine de
                                 ME9 - Remplacement de TP défectueux
                                                                                     Meyrin

                                 MEQ59 - Tests compensateur (TE-EPC)                 Réseau machine de Meyrin

                                 LHC8 - Câblage sur compensateur pour TE-EPC         Réseau SG du LHC,
                                 Transfert du réseau machine du LHC8 sur la boucle   Réseau machine LHC8,
                                 LHC (SG) + WAP                                      ATLAS, SPS

                                 Libération de chaque disjoncteur 400KV pour         Réseaux machine SPS
                                 modification + installation DGA                     Zone Nord

                                 Transfert du CERN du BE2 vers BE1 (400/66kV)        Réseaux CERN

                                                                                     Réseau SG du LHC
Manœuvre avec coupure            Transfert du réseau machine LHC5 et LHC6 sur
                                                                                     Réseau machine LHC5 & 6,
Manœuvre sans coupure            boucle LHC
                                                                                     ATLAS, SPS

                        07/10/2020                     Manoeuvres EN-EL fin 2020 - V3                   13
EN-EL - Manœuvres en Novembre
                                                                                          réseaux affectés
                                                                                      Réseaux secours LHC5 &
                             LHC5 & LHC6 – Maintenance Diesel
                                                                                      LHC6

                                                                                      Réseau Meyrin, ATLAS,
                             Meyrin - Tests filtre (TE-EPC)
                                                                                      SPS, ZN, LHC18

                             BE - Consignation de chaque transformateur 400KV pour    Réseaux machine SPS
                             maintenance (DGA + WAP)                                  Zone Nord

                             BE - Tests compensateur BEQ3 (TE-EPC) – Transfert de     Réseaux machine SPS
                             charges                                                  Zone Nord

                             LHC4 - Tests compensateur (TE-EPC)                       Réseaux machine LHC4

                                                                                      Réseaux SG et machine
                             SPS - Reconfiguration réseau SG et machine
                                                                                      SPS

                                                                                      Réseaux SG et machine
                             BA4 - Mise hors tension liaisons BA3  BA4
                                                                                      SPS

                                                                                      Réseaux SG et machine
                             BA4 - Tests Local Scada
                                                                                      SPS

Manœuvre avec coupure
Manœuvre sans coupure

                        07/10/2020                       Manoeuvres EN-EL fin 2020 - V3                  14
EN-EL - Manœuvres en Décembre
                                                                                          réseaux affectés

                             LHC8 - Tests compensateur (TE-EPC)                       Réseaux machine LHC8

                             Consignation ME4 (Meyrin)                                Voir plan ci-dessous

Manœuvre avec coupure
Manœuvre sans coupure

                        07/10/2020                       Manoeuvres EN-EL fin 2020 - V3                      15
EN-EL - Points Divers
• Test à planifier :                                                         réseaux affectés

                     Zone Administrative - Test AUG                      Coupure Zone Administrative

                                                                         Réseau machine + SG LHC5
                     LHC5 - Test AUG
                                                                         + Arc 4-5 5-6

                     Prévessin - Test AUG                                Réseau SG Prévessin

                                                                         Réseau machine + SG
                     LHC18 - Test AUG
                                                                         LHC18

            07/10/2020                      Manoeuvres EN-EL fin 2020 - V3                     16
Questions

        07/10/2020   Manoeuvres EN-EL fin 2020 - V3   17
Vous pouvez aussi lire