North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and ...
←
→
Transcription du contenu de la page
Si votre navigateur ne rend pas la page correctement, lisez s'il vous plaît le contenu de la page ci-dessous
North Area Maintenance weeks and AUG tests Feedback from users & lessons learned Additional activities for EN-EL contractor List of activities and follow-up EN-EL calendar LS2 planned maneuvers D. Bozzini on behalf of EN-EL, 13 October 2020
Feedback from users & lessons learned EN-EL invited to report on North Area maintenance and AUG tests at the ENTM planned for Thursday 15 October 2020 Request made to main users and stakeholders to provide feedback on the four following topics Affected systems Malfunctions (causes, consequences and measures taken) Coordination and planning Suggestions for improvement Valuable feedback received so far from: F. Duval (EP) J. Devine (EP) draft in approval state TI (BE) Presentation to EATM after ENTM conclusions and recommendations 3
Examples of maintenance activities Maintenance 18 kV Magrini switchgear – General Services network 4 switchgear, 35 feeders, dating from 70’, includes busbars & ground switch-disconnectors Last maintenance performed in 2005, should be done every 10 Before After yrs. 100% completed Switchgear dangerous to operate, requiring maintenance < 10 yrs. “Risque de désaxage des volets en ferraille engendrant un court- circuit franc pendant les manœuvres de consignation” “Remplacement visserie HS sur connexion secondaire transformateur de courant (TC) dans EMD2/A82, risque d’explosion du TC” 4
Examples of maintenance activities Scheduled corrective intervention on a LV switchboard (sub-distribution) following visual inspection and routine visits performed during machine operation “Risque de mauvaise connexion dans le temps, départ de feu” Before After Consolidation AUL system in EHN1 following malfunctioning observed by EP in August 2020 Replacement of one tripping coil and three circuit breakers 5
Actions initiated and planned to be done during LS2 Study for replacement of the following UPS systems EBS21/BL4 EBS22/A81 EBS21/A85 EHN1 Replacement of batteries of the following UPS systems (already part of the EN- EL program) EBS21/A80 EBS24/A80 EBS21/A81 EBS24/A81 EBS21/A82 EBS24/A82 EBS21/B81 Completion of 48V system in EHN1 6
List of activities and follow-up Goal is to grant a sufficient workload to EN-EL contractor Identification of activities that can be done in the coming months, according to infrastructure availability and accessibility Common EN-EA / EN-EL table for regular update and follow-up at the EATM and/or EACM 8
List of activities and follow-up Urgent Still to be In Under Study Estimation Priority Area Zone Description New EN-EL Status Date Budget Comments (2020) Confirmed Pipeline (EA) (kCHF) 0 EHN1 PPE144 nouvelle installation x in pipeline mid-Oct. 100 89955 starts mid-October 0 EHN1 PPEs Installation CROME (RP) x in pipeline Nov. RP after PPE144 0 EHN1 PPEs campagne de décablage PPE158, 164, 112, 172 x in pipeline 15 55455 already discussed (cable cleaning campaign) 0 NA 907/908 Projet Monitoring Gaz : mécanique et tirage câbles x x Philippe 95428 1 week of work, 907/908, budget approval pending EHN1, work already done with J. Devine (for ??? ALL ??? 0 EHN2, various EL non-conformities (AUL replacements/repair) x on-going AULs)? ECN3 nouvelle zone de stockage IRRAD (eclairage, 1 East Area IRRAD x x 2021 5 55456 50/50% budget split between EA and DT puissance) Réaménagement de la zone : as from mid- 1 EHN1 H6-H8 x x x 20 89955 required for 2021 operation (MADMAX) dépose (décablage, e-a-c, boitiers) Nov. progressive replacement of AULs, requires EP 1 EHN1 various AUL->AUG x x x 2021 55455 approval (DSO discussion on-going) electrical distribution, needs detailed study with all 1 EHN1 barack gaz dépose + réinstallation? x dismantling x 2021 89300/55455 service providers -> work needs to be finished prior 2021 operation pending 1 EHN1 AWAKE installation EL nouvelle salle laser x AWAKE ticket issued, pending approbation approbation required for 2021 operation, but finalization of Aménagement pour 1 EHN2 PPE211 x x 89955 implementation study required before EL work can NA64mu/Amber-COMPASS/Muon-e be considered 1 ECN3 TCC8 ajouter un coffret de prises (tri-16A + 220V-10A) x 2 55455 minor works for a vacuum pump already in ASAP si feu vert (financier pour ATLAS et 1 LHC ZDC ZDC ATLAS : Cheminement x Gianluca 20/2021 15 ATLAS discussion organisationnel pour LHC coordination ACE) already in ASAP si feu vert (financier pour ATLAS et 1 LHC ZDC ZDC ATLAS : tirage de câbles x Gianluca 20/2021 40 ATLAS discussion organisationnel pour LHC coordination ACE) already in Procurement des câbles en cours donc sera basculé 1 LHC RPD RPD ATLAS : tirage de câbles x Gianluca 2021 55 ATLAS discussion en 2021 2 days of work, (F. Duval - NA62), 1 ECN3 NA62 cable installation x x Philippe NA62 surface/underground 1 ALICE UX25 Alice CV, installation de 8 câbles CR4 UX25 x Philippe ALICE already in 1 Meyrin bldg 2004 rewamping installation CV x Gianluca Feb-21 CV février 2021 discussion 1 LHC SND x Philippe SND/EA see ECR (2020 + 2021) 1 EHN1 M1 NA-CONS approved Jan/Feb-21 135 NA-CONS required for 2021 operation refused VSC and NA-CONS (Yacine as contact) -> required 1 NA TCC2 vacuum cable installation (one additional) x Yacine 20/2021 initially for 2021 operation initially not not 2 East Area galleries dépose cables DC + signaux x x considered 2020/2021 10 55456 can be started anytime (EPC work already done) concerned for LS2 2 East Area galleries dépose Terminal Boxes x x 2020/2021 3 55456 minor works 2 EHN1 PPE124 eclairage additionel x a.s.a.p. 2 55442 minor works pending 2 EHN1 HNA272 campagne de décablage 272 x ticket created RQF1614906 approbation YETS 21/22 beneficial to advance? -> needs to maintain 2021 2 EHN1 3.3kV transformer consolidation approved or ? Earlier operation availability routing not beneficial to do in 2021 -> will be done in YETS 3 EHN1 Morpurgo NA-CONS YETS 21/22 under study 21/22 -> DC cabling could be possibly anticipated request 4 LHCb Velo EL involved? -> LHCb didn't keep request dropped 9
EN-EL calendar LS2 planned maneuvers Presentations given by B. Saint Sulpice at the TIOC on 7th October 2020
Calendar EN-EL of LS2 activities 07/10/2020 Manoeuvres EN-EL fin 2020 - V3 11
Calendar EN-EL of LS2 activities noir : Validé par les utilisateurs, les Validé coordinations et EN/EL rouge : Non validé. En cours de validation par les utilisateurs, les coordinations ou EN/EL 07/10/2020 Manoeuvres EN-EL fin 2020 - V3 12
EN-EL - Manœuvres en Octobre réseaux affectés BE - Tests compensateur BEQ1 (TE-EPC) – Réseaux machine SPS Transfert de charges Zone Nord LHC2 - Tests compensateur (TE-EPC) Réseaux machine LHC2 BE - Tests compensateur BEQ2 (TE-EPC) – Réseaux machine SPS Transfert de charges Zone Nord Réseaux SG et machine de ME9 - Remplacement de TP défectueux Meyrin MEQ59 - Tests compensateur (TE-EPC) Réseau machine de Meyrin LHC8 - Câblage sur compensateur pour TE-EPC Réseau SG du LHC, Transfert du réseau machine du LHC8 sur la boucle Réseau machine LHC8, LHC (SG) + WAP ATLAS, SPS Libération de chaque disjoncteur 400KV pour Réseaux machine SPS modification + installation DGA Zone Nord Transfert du CERN du BE2 vers BE1 (400/66kV) Réseaux CERN Réseau SG du LHC Manœuvre avec coupure Transfert du réseau machine LHC5 et LHC6 sur Réseau machine LHC5 & 6, Manœuvre sans coupure boucle LHC ATLAS, SPS 07/10/2020 Manoeuvres EN-EL fin 2020 - V3 13
EN-EL - Manœuvres en Novembre réseaux affectés Réseaux secours LHC5 & LHC5 & LHC6 – Maintenance Diesel LHC6 Réseau Meyrin, ATLAS, Meyrin - Tests filtre (TE-EPC) SPS, ZN, LHC18 BE - Consignation de chaque transformateur 400KV pour Réseaux machine SPS maintenance (DGA + WAP) Zone Nord BE - Tests compensateur BEQ3 (TE-EPC) – Transfert de Réseaux machine SPS charges Zone Nord LHC4 - Tests compensateur (TE-EPC) Réseaux machine LHC4 Réseaux SG et machine SPS - Reconfiguration réseau SG et machine SPS Réseaux SG et machine BA4 - Mise hors tension liaisons BA3 BA4 SPS Réseaux SG et machine BA4 - Tests Local Scada SPS Manœuvre avec coupure Manœuvre sans coupure 07/10/2020 Manoeuvres EN-EL fin 2020 - V3 14
EN-EL - Manœuvres en Décembre réseaux affectés LHC8 - Tests compensateur (TE-EPC) Réseaux machine LHC8 Consignation ME4 (Meyrin) Voir plan ci-dessous Manœuvre avec coupure Manœuvre sans coupure 07/10/2020 Manoeuvres EN-EL fin 2020 - V3 15
EN-EL - Points Divers • Test à planifier : réseaux affectés Zone Administrative - Test AUG Coupure Zone Administrative Réseau machine + SG LHC5 LHC5 - Test AUG + Arc 4-5 5-6 Prévessin - Test AUG Réseau SG Prévessin Réseau machine + SG LHC18 - Test AUG LHC18 07/10/2020 Manoeuvres EN-EL fin 2020 - V3 16
Questions 07/10/2020 Manoeuvres EN-EL fin 2020 - V3 17